KISSIMMEE RIVER RESTORATIONPROJECT STATUS
Completed Construction on Local Levees in Pool C
Initiated Construction for Reach 1 Backfill $10.8M
Construction at S-65 nearly complete
Construction underway at C-35 & C-36
Award Contract for S-65A - Sep 1999 (8A)
Award Contract for Pool A Gapping - Sep 1999
Award Contract for C-37 - Oct 1999